This section explains the University contracting process and provides assistance to departments in the development, drafting, and processing of contracts.

A proposed contractual relationship or transaction that would commit University resources of any nature must be reduced to a written agreement. The agreement must be approved by appropriate University officials and signed by a University officer who has received written delegated authority from the Board of Regents or the President to sign such agreements. See 10.10.

Contract Defined

A contract is an agreement between two or more parties creating obligations that are enforceable or otherwise recognizable at law.

Central Contract Administration Offices

Several central administration offices process contracts for the University.

Office Contract Types Other BPPM References

Finance and Administration
(telephone 335-5524)

 

 

 

 

 

 

 

Real Estate (sales/purchases/leases)

20.45

 

 

 

 

 

 

 

WSU Facilities Use
Interlocal and Interagency Agreements (between WSU and other governmental entities)
Revenue-generating Agreements
Performances (Beasley)
Academic Programs (domestic and international)
Affiliation Agreements (internships/student teaching)
Miscellaneous Agreements

Purchasing Services
(telephone 335-3541)

 

 

 

Personal Services Contracts 70.50
Purchased Services 60.01
Equipment Chapter 70
Software 70.24
Goods Chapter 70
Performances (not Beasley) 70.21
Office of Grant and Research Development (OGRD)
(telephone 335-9661)
Sponsored Projects
 
 

Chapter 40

 

Human Resource Services (HRS)
(telephone 335-4521)
Personnel
 
Chapter 60
 
Provost's Office
(telephone 335-5581)
Faculty Employment
 
60.11, 60.25
 
Facilities Services, Capital
(telephone 335-5571)
Major Capital Construction (including consulting)  
Facilities Services, Operations (telephone 335-9000) Minor Capital Construction (including consulting) 80.56
 

General Questions

For answers to general questions about contract processing, contact the Office of Finance and Administration; telephone 335-5524.

Complex Agreements

Any central contract administration office may request assistance from the Associate Vice President for Finance when an agreement is unusually difficult to draft or negotiate or requires executive-level involvement.

CONTRACT PROCESSING PROCEDURES

To process a contract, departmental personnel initially contact the appropriate central contract administration office. (See table above.)

Exceptions

The procedures in this section do not apply to contracts processed through the Office of Grant and Research Development (OGRD), Facilities Services, Capital, and Facilities Services, Operations.

Standard Procedures

The standard procedures in this section apply to contracts processed by Finance and Administration, Purchasing Services, and Human Resource Services (HRS).

The proposing department is responsible for negotiating and preparing the initial draft of the agreement in accordance with this and other applicable BPPM sections.

The central contract administration office provides model agreements for use as contract templates.

Contracting Steps

Contracting is made up of five distinct steps: negotiation, drafting, review, approval, and performance.

NOTE: During the negotiation, drafting, and review stages of contract preparation, the negotiator and other University representatives often provide the other party with information regarding contract terms and conditions. The response from the other party may require additional negotiation, redrafting, and further review.

Negotiation

The proposing department is responsible for negotiating the terms and conditions that are unique to the requested agreement, e.g., scope of work, quantity, quality, price, deliverables, timelines, work product. The terms and conditions include all rights, responsibilities, and obligations of the contracting parties.

The individual with the most knowledge of the desired relationship or transaction should conduct the negotiations. The proposing department may request assistance with negotiations from Purchasing Services or other central contract administration office.

The negotiator is to make it clear to other parties that ultimate University approval of the contract can only be conferred by a University official holding delegated authority to sign contracts on behalf of the University.

Drafting

The proposing department is responsible for originating contract drafts and providing supporting information. The contract draft must include standard University terms and conditions applicable to the type of contract being drafted. The appropriate central contract administration office may provide assistance. (See table above.)

Specific model templates are available from the appropriate central contract administration offices. See the agreement template in the PDF version of 10.11.8-11 for general guidance regarding agreement preparation. This general template may be used if the central contract administration office does not provide an applicable model template.

NOTE: The use of a model template substantially expedites the University review and approval process.

Review

The proposing department completes a Contract Review Sheet that summarizes the proposed contract and indicates potential commitments of University resources, and provides for signatures of reviewing officers. The Contract Review Sheet is routed with the proposed contract.

See 10.11.7 for a PDF template of the Contract Review Sheet. The template may be completed onscreen and printed.

The following information must be included on the Contract Review Sheet.

Central Contract Administration Office

Route the initial draft of the proposed contract and the completed Contract Review Sheet to the appropriate central contract administration office. (See table above.)

EXCEPTION: See 40.02 for review and approval of sponsored agreements.

The proposing department and central contract administration office refine and revise the draft until the reviewing parties are satisfied that the contract is in final form.

The proposing department should allocate adequate time for this part of contract preparation. Early review of the draft by the central contract administration office usually expedites the contract preparation.

Other Review

When a draft contract involves the following issues, the central contract administration office ensures that appropriate offices review the document.

Approval

The proposing department obtains administrative approval. The appropriate central contract administration office obtains approval as to form and final approval.

Administrative Approval

The proposing department is responsible for obtaining appropriate administrative approval to proceed with the agreement, usually before the contract is in final form.

Written approval by unit administrators constitutes affirmation that the approvers have read and reviewed the proposed contract that documents the transaction or relationship, understand the commitments and risks undertaken, have the funds or resources to support contract requirements, and recommend the approval and execution of the agreement.

A department or college may impose internal approval processes in addition to the University requirements described here.

Academic Departments

A contract originating with an academic department should be approved by the dean or equivalent area administrator.

Nonacademic Departments

A contract originating with a nonacademic department should be approved by the responsible unit manager, director, and vice president or associate vice president or equivalent area administrator.

Approval "As to Form"

The central contract administration office obtains approval "as to form" from the Office of the Attorney General when the contract deviates from one of the model templates.

This approval merely indicates that all elements necessary to create a formal contract are present and that there is nothing that is contrary to state law in the agreement. Approval as to form does not confer approval of the proposed transaction on a policy level or indicate whether or not the proposed agreement and terms are beneficial or detrimental to the University.

This step may take several days. The central contract administration office should route the contract to the Office of the Attorney General several days in advance of any deadline to provide adequate review time.

Final Approval

Signature by an officer with delegated contract authority constitutes the official University final approval of the contract. This signature may be obtained either before or after signatures by other parties to the agreement. If any party seeks to make changes to a previously-signed contract, all signers of the contract must initial such changes.

Only those with delegated contract authority originating with the Board of Regents may sign agreements for and on behalf of the University. See 10.10. The Board of Regents by resolution has delegated certain contract authority to the President. The President has delegated in writing specific parts of that authority to the Vice President for Finance and Administration and other specifically named University officials. NOTE: Certain contracts require the approval of the Board of Regents, e.g., construction contracts over $500,000.

Performance

The proposing department is responsible for the contract performance. Likewise, any obligations indicated in the contract remain with the unit, department, or college requesting the relationship or transaction. As such, during the administrative review the approving dean or director should carefully review the agreement for commitments the department will be required to provide or elicit from other parties.

If during the performance of the contract, it becomes apparent that contract changes are required, the proposing department initiates a revised contract proposal and processes the proposed contract using the procedure in this section. Such changes might include extending the time of performance, changing the scope, or changing costs.

Problem Resolution

The proposing department should seek assistance from the responsible central contract administration office when resolving contract problems. If the resolution results in a change in terms and/or conditions, the new contract must be approved by a University officer holding delegated signature authority. If the problem involves litigation or potential litigation, the central contract administration office seeks the assistance of the Attorney General's Office.

See the PDF master form:
10.11.7: Contract Review Request
Complete and print as needed

Use a model agreement provided by the central contract administration office when preparing a contract. If no model agreement exists, refer to the Agreement Template on 10.11.8-11.